Back to Menu No.01-01-02

Change Cost Element Group (KAH2)

Menu: Accounting > Controlling > Cost Element Accounting > Master Data > Cost Element Group > Change

Process Overview: Change (add, delete, or remove) a Cost element group.


Screen 1:

Operation Process:

1. {{Cost element group}} Enter the Cost element group. (Ex. 'ZZ00-CE01')
2. Click [Enter].

Processes:(1) New creation (2) Remove  (3) Deletion


(1)New creation (Ex. Creating "ZZ00-CE13" at the same level as "ZZ00-CE12")

Screen (1)-1:

Operation Process:

1. Positions the cursor to the level to be registered. (EX.'ZZ00-CE12')
2. Click [Insert Cost element group on same level].
3. {{Cost Element Group}} Enter the Cost element group. (Ex.'ZZ00-CE13')
4. {Cost Element Group Description} Enter the Description of the Cost element group.

Screen (1)-2:

Operation Process:

1. Click [Save].

(2)Remove (Ex. Remove "ZZ00-CE13" from "ZZ00-CE01")

Screen (2)-1:

Operation Process:

1. Position the cursor to the target Cost element group.
2. Click [Select].
3. Click [Remove].
4. Click [Save].

Remarks:

  1. Selecting [Remove] removes only the relevant Cost element group within the current hierarchy.
  2. If not saved after remove, the remove will be cancelled.

(3)Deletion (Ex. Deleting ZZ00-GRP13)

Screen (3)-1:

Operation Process:

1. Position the cursor to the target Cost element group.
2. Click [Select].
3. Click [Delete].

Screen (3)-2:

Operation Process:

1. Click [Delete].
2. Click [Save].

Remarks:

  1. Selecting [Delete] deletes the relevant Cost element group from all Cost element groups.
  2. Once the deletion is processed, it cannot be cancelled.

Copyright(c) MITSUI KINZOKU YOURSOFT Inc.