Back to Menu No.04-05-05

List: Cost Elements by Order (S_ALR_87012997)

Menu: Accounting > Controlling > Internal Orders > Information System > Reports for Internal Orders > Plan/Actual Comparisons > List: Cost Element by Order

Process Overview: Display a list of Cost elements by Internal Order.


Screen 1:

Operation Process:

Selection values
1. {{Controlling Area}} Enter the target Controlling Area.
2. {{Fiscal Year}} Enter the target Fiscal Year.
3. {{From Period}} Enter the target starting Period.
4. {{To Period}} Enter the target ending Period.
5. {{Plan Version}} Enter '0'(Plan/Actual Version).
Selection groups
6. {Order Group} or Enter the target Order Group or Order.
{Or value(s)}  
7. {Cost Element Group} or Enter the target Cost Element Group or Cost Element.
{Or value(s)}  
8. Click [Execute].

Screen 2:

Operation Process:

1. More > Goto > Scroll horizontal To move column right and left. ([To the far left], [Page left], [Page Right], [To the far Right])
2. More > Goto > Variation To change hierarchy level. ([Variation Previous level], [Variation left], [Variation right], [Variation next level])
3. More > View > Expand section, Collapse section To expand section or collapse.
4. More > Setting > Column attributes To change column width. (After putting a cursor on any column, select the menu pass.)
5. To display the other report. ([Call up report]) (After selecting a specifying amount column, click the button.)
6. To replace the list by Excel Sheet. ([Options / Office Integration])

Remarks:

1. Enable to drill-down by double-cricking a specifying line.

Copyright(c) MITSUI KINZOKU YOURSOFT Inc.