Back to Menu No.02-05-02

Cost Centers: Actual/Plan/Variance (S_ALR_87013611)

Menu: Accounting > Controlling > Cost Center Accounting > Information System > Reports for Cost Center Accounting > Plan/Actual Comparisons > Cost Centers: Actual/Plan/Variance

Process Overview: Display a list of Cost of Planning, Actual and Variance value by the Cost center or the Cost element.


Screen 1:

Operation Process:

Selection values
1. {{Controlling Area}} Enter the target Controlling Area.
2. {{Fiscal Year}} Enter the target Fiscal Year.
3. {{From Period}} Enter the target starting fiscal Period.
4. {{To Period}} Enter the target ending fiscal Period.
5. {{Plan Version}} Enter '0'(Plan/Actual version).
Selection groups
6. {Cost Center Group} or
{Or value(s)}
Enter the target Cost Center Group or Cost Centers.
7. {Cost Element Group} or
{Or value(s)}
Enter the target Cost Element Group or Cost Elements.
8. Click [Execute].

Screen 2:

Operation Process:

1. More > Goto > Scroll horizontal Move column right and left. ([To the far left], [Page left], [Page Right], [To the far Right])
2. Display hierarchy of the cost center group. [Navigation on/off]
3. More > Goto > Variation Change hierarchy level. ([Variation previous level], [Variation next level], [Variation left], [Variation right])
4. More > View > Expand section, Collapse section Expand section or collapse.
5. More > Setting > Column attributes Change column width. (After putting a cursor on any column, select the menu pass.)
6. Display the other report. ([Call up report]) (After selecting a specifying amount column, click the button.)
7. To replace the list by excel sheet, click [Options / Office Integration].

Remarks:

1. Enable to drill-down by double cricking a line.

Copyright(c) MITSUI KINZOKU YOURSOFT Inc.